You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.

Tošanovice-Žukov Bridge, Czech Republic

Prosjektdetaljer

Location: Ostrava, Tsjekkia

Design: steel composite bridge
Length: 720 m

PERI utstyr

The strut axes open out from 6.50 m to 9.00 m in the centre of the bridge.

Kunder

Metrostav a.s., Division 4, Prague

Kundens fordeler

  • flexible connecting possibilities for steel walers, scaffold tubes, heavy-duty spindles and tie rods
  • can be adapted to various main beam spacings
Martin Šimek, Site Manager
Martin Šimek
Site Manager

The erection of steel composite bridges is considerably easier and much faster with the PERI formwork carriage construction.

PERIs løsninger

Two modular formwork carriages from the VARIOKIT system