-
##project.benefits.item.headline##at peak times 8,000 m² of slabs were formed, concreted and realised per week
-
##project.benefits.item.headline##reduced on-site material requirements plus cost savings thanks to coordination by PERI Project Manager in close cooperation with the Site Manager
Prosjektet
Bilder fra prosjektprosessen
##project.requirementsAndSolutions.headline##
Jürgen Feierle
Project Manager
With the PERI slab table solution at peak times we are realising 8,000 m² of slab formwork per week – with all beams and with floor heights of up to 7 m. By combining with SKYDECK we are even able to continue working in strong winds without interruption and can also minimise crane dependency. PERI construction site support offers us technical solutions in the shortest time and also supplies large volumes of materials within just 2 days.
##SalesContactsSectionHeadline##
Ring oss gjerne på +47 32 20 49 40 eller kontakt en av våre selgere.