Re-facing 25 blocks of flats, Sundparken, Horsens, Denmark
SCANDECK allows the tradesmen to work safely and more efficiently
A successfull scaffold is planned considering all the requirements of the client and the tradesmen which leads to a successfull project.
It may seem that the supply of a scaffold 2.35 m wide is extravagant until you consider the requirements put on it.
15 different trades were working on the re-facing and all their material had to be stored on the scaffold as the tenants remained in occupation during the full program of renovation.
42,000 m² of PERI UP SCANDECK met the requirements of all trades.
erection without any bracing
anchored at each standard at 12.00 m level only
minimal adaption of scaffolding even for the bricklayer