Athens, Greece, Construction for the Olympic Games:

Main Press Centre With an area of more than 52,000 m², this modern building complex is the largest of its kind in the history of the Olympic Games. For the walls in the basement area, singlefaced formwork with DOMINO wall panels mounted on SB1 brace frames were used. Forming lifting units made it possible to finish the cycles with only a few crane lifts and bring them quickly to the next section. Depending on their availability, TRIO and DOMINO panels were used for the pillars. Even for cross-sections of up to 1.20 x 1.20 m where the DOMINO system was used no through anchors were needed.